VDOT News - Northern Virginia
RELEASE: CONTACT: |
IMMEDIATE Michelle Holland 703-586-0487 Michelle.Holland@vdot.virginia.gov |
NOVA-190596 Feb. 9, 2022 |
Demolition of Old I-66 Ramp Retaining Walls at Stringfellow Road to Continue This Weekend, February 11-14, During Daytime and Overnight Hours
Stringfellow Road North reduced to one lane, ramps to I-66 East/from I-66 West to be closed; Stringfellow Road ramps also closed Wednesday night, Feb. 9
FAIRFAX – Demolition of the old barrier and retaining walls along the I-66 ramps at Stringfellow Road will continue this weekend, February 11-14, during the daytime and overnight hours. For crews to safely perform this work, the I-66 ramps to and from Stringfellow Road will be closed beginning at 10:30 p.m. Friday, February 11, continuously through 5 a.m. Monday, February 14. Stringfellow Road North approaching I-66 will also be reduced to a single travel lane during this period. This work is part of the Transform 66 Outside the Beltway Project.
In addition, the I-66 ramps to and from Stringfellow Road will be closed tonight, Wednesday night, February 9, from midnight to 4 a.m.
Drivers should expect delays if traveling in this area and consider using alternate routes.
What Neighbors Should Expect:
- Crews will continue to remove the old barrier along the I-66 East ramp, and begin demolition of the retaining walls adjacent to the I-66 ramps at Stringfellow Road. This work will occur during both the daytime and overnight hours, beginning Friday night, February 11, continuously through Monday morning, February 14.
- Demolition of the old barrier and retaining walls involve breaking up the old concrete using jackhammers, saw cutters, and hoe rams.
- Work is anticipated to require 10-12 nights of demolition activity to complete.
- All work is weather dependent and will be rescheduled if inclement conditions occur.
- Information about traffic impacts and demolition progress will be posted on outside.transform66.org/stringfellow.
What Drivers Should Expect:
Wednesday night, February 9
Ramp from I-66 West to Stringfellow Road
Ramp from Stringfellow Road to I-66 East
- The ramps will be closed tonight between midnight and 4 a.m.
Friday, February 11, through Monday, February 14
Ramp from I-66 West to Stringfellow Road
Ramp from Stringfellow Road to I-66 East
- The ramps will be closed for demolition of the old I-66 bridge abutments and retaining wall beginning at 10:30 p.m. on Friday, February 11, continuously through 5 a.m. Monday, February 14.
- The ramps will reopen by 5 a.m. Monday morning.
Stringfellow Road North between Westbrook Drive and Fair Lakes Boulevard
- Stringfellow Road North will be reduced to a single travel approaching the I-66 overpass for demolition of the old I-66 bridge abutments and retaining wall beginning at 10:30 p.m. Friday, February 11, continuously through 5 a.m. Monday, February 14.
- All lanes will reopen by 5 a.m. Monday morning.
Demolition Progress to Date:
- Crews completed demolition of the old I-66 bridge decks over Stringfellow Road in November 2021.
- Demolition of the old bridge abutments and the old barrier along I-66 West was completed during the weekend of February 4, 2022.
The I-66 bridges over Stringfellow Road are being widened to accommodate the new I-66 Express Lanes and provide room for any future mass transit along I-66.
Weekly updates will be available at Transform66.org and on Twitter @VaDOTNOVA. To receive project updates automatically by email, sign up here.
###
Demolition progress along Stringfellow Road as of Feb. 8, 2022
Tweet
Information in VDOT news releases was accurate at the time the release was published. For the most current information about projects or programs, please visit the project or program Web pages. You may find those by searching by keyword in the search Virginia DOT box above.