- Removal of bridge beams is planned for Monday night, Feb. 24. Demolition of two bridge piers is planned for Tuesday, Feb. 25, through Friday night, Feb. 28.
- Five nights of demolition-related activity remain during this phase. The schedule will be adjusted if weather delays occur.
- Nearby residents may hear unavoidable construction-related noise during demolition operations.
- Drivers should plan for nightly lane closures for the demolition work on I-66 East between Route 50 and Route 123 with occasional 20-minute stoppages between midnight and 4 a.m. (5 a.m. on weekends).
Crews completed removal of the concrete bridge deck of the Route 123 ramp over I-66 on Sunday night, Feb. 23. Demolition activities that don't require multiple lane closures on I-66 will occur during daytime hours.
Demolition of the I-66 bridges over Fairfax County Parkway (Route 286) is also scheduled to continue this week. Nightly lane closures on I-66 East and Route 286 North and South will be implemented to safely accommodate this work.
All work is weather dependent and will be rescheduled if inclement conditions occur. Find additional details on planned traffic closures at www.Transform66.org.