VDOT News - Northern Virginia

RELEASE:

CONTACT:
IMMEDIATE

Michelle Holland 703-586-0487
Michelle.Holland@vdot.virginia.gov

NOVA-158804

April 17, 2020



Extended and Long-Term Lane Closures Begin Next Week On I-66
Areas Include I-66 near Vienna; I-66 West near Manassas; Two I-66/I-495 Ramps; and Route 28 near E.C. Lawrence Park

FAIRFAX – Several long-term lane closures are scheduled to begin Monday night, April 20, on I-66 between I-495 and Route 29 (Lee Highway) Gainesville for construction on the Transform 66 Outside the Beltway Project. These extended closures are possible due to lower traffic volumes in recent weeks, and will allow crews greater flexibility and more time each day to complete their tasks. VDOT will continue to monitor traffic and adjust these lane closures as needed.

Details include:  

Ramp from I-66 East to I-495 North
Ramp from I-495 North to I-66 West

  • Beginning 8 p.m. on Monday, April 20, the left lane will be closed on the ramp from I-66 East to I-495 North, and the left lane will be closed on the ramp from I-495 North to I-66 West. The right lane will remain open on both ramps.
  • Crews will be constructing new I-66 bridge piers.

Lane closures on I-66 East and West between Blake Lane and Gallows Road

  • Beginning 8 p.m. on Monday, April 20, the HOV lane on I-66 West will be closed between Gallows Road and Vaden Drive.   
  • Beginning 8 p.m. on Wednesday, April 22, the HOV lane on I-66 East will be closed between Blake Lane and Gallows Road.
  • Three travel lanes will be available for all traffic.
  • Crews will be conducting various construction activities in this area.

Ramp from Route 50 East to I-66 East

  • Beginning the week of April 20, the ramp from Route 50 East to I-66 East will be reduced to a single lane.

Lane closures on Route 28 North and South between I-66 and the old E.C. Lawrence Park athletic fields entrance

  • Beginning Monday, April 20, between 8 p.m. and 6 a.m. nightly, two lanes will be closed on Route 28 South from the old E.C. Lawrence Park athletic fields entrance to I-66. 
  • Beginning Tuesday, May 5, between 8 p.m. and 4:30 a.m. nightly, two lanes will be closed on Route 28 North from I-66 to the old E.C Lawrence Park athletic fields entrance. This work might begin earlier than May 5, depending on other construction progress on Route 28.
  • The closures are needed for paving operations. 

Lane closures on I-66 West between Route 234 Business (Sudley Road) and Route 29 Gainesville

  • Beginning Monday, April 20, the HOV lane on I-66 West from Route 234 Business to Route 29 Gainesville will be closed.
  • Three travel lanes will be available for all traffic between noon and 8 p.m.
  • Between 6 a.m. and noon daily, two lanes will be closed, leaving two lanes open.
  • Between 8 p.m. and 6 a.m. nightly, three lanes will be closed, leaving one lane open.
  • These closures will allow for extensive paving operations needed to shift traffic to the outside (right side) for construction of the Express Lanes in the median (left side). 
  • Similar paving operations are scheduled to occur on I-66 East between Route 29 Gainesville and Route 234 Business beginning in late May (date subject to change depending on other paving progress).

Construction schedules are subject to change based on weather and construction progress. 

Learn more about the I-66 Outside the Beltway Project and sign up for project updates and lane closure alerts at Transform66.org.

On Twitter, follow VDOT Northern Virginia at @vadotnova.

###



Information in VDOT news releases was accurate at the time the release was published. For the most current information about projects or programs, please visit the project or program Web pages. You may find those by searching by keyword in the search Virginia DOT box above.

Page last modified: June 2, 2023