VDOT News - Northern Virginia

RELEASE:

CONTACT:
IMMEDIATE

Ellen Kamilakis
ellen.kamilakis@vdot.virginia.gov

NR19-074

July 29, 2019



Princedale Road Pipe Replacement Progressing in Prince William
VDOT crews installing new pipe through late August


DALE CITY – Virginia Department of Transportation (VDOT) structure and bridge crews continue work to replace a large stormwater pipe on Princedale Drive that failed after heavy rains on July 4, causing a sinkhole. The road is expected to remain closed between Saddler Lane and Roundtree Drive for four more weeks, weather permitting.

The 84-inch diameter galvanized metal pipe had been conveying water for a tributary of Neabsco Creek. After several inches of rain in a short period of time on July 4, the force of the water pushed the pipe into the creek, causing the asphalt above to fail.

Current Status

  • Work was done on July 6 to relieve water pressure within the creek.
  • Crews stabilized utility pipes on July 7.
  • A hydraulic assessment was completed that recommended two 130’ long runs of 60-inch diameter concrete pipes to be installed, as well as new headwalls.
  • On July 22, crews began pipe installation that is expected to continue through late August.                                

Follow VDOT Northern Virginia on Twitter for more updates: @vadotnova

                                                                                                END



Information in VDOT news releases was accurate at the time the release was published. For the most current information about projects or programs, please visit the project or program Web pages. You may find those by searching by keyword in the search Virginia DOT box above.

Page last modified: Aug. 17, 2023